Quick Reference
Menu map, demo-data codes and statuses
Menu Map
| Group | Models |
|---|---|
| Rehabilitation Delivery | Rehabilitation Work, Work Inspection, Work Material, Rehabilitation Campaign, Rehabilitation Prescription, Disturbance Event |
| Domains & Land Use | Closure Domain, Land Availability Event, Domain Land Use, Domain Objective, Post Mining Land Use |
| Completion Criteria | Completion Criterion, Domain Criterion, Criterion Assessment |
| Monitoring & Results | Monitoring Event, Monitoring Result, Monitoring Schedule, Monitoring Program, Monitoring Location |
| Certification & Relinquishment | Certification Application, Certification Criterion, Relinquishment Application, Relinquishment Domain, Closure Review |
| Risk, Findings & Actions | Closure Risk, Finding, Corrective Action |
| Stakeholders & Commitments | Closure Commitment, Stakeholder, Engagement Event |
| Closure Cost | Closure Cost Estimate, Closure Cost Item, Actual Closure Cost |
| Plans & Obligations | Closure Plan, Closure Objective, Closure Assumption, Plan Requirement Link, Requirement, Source Document, Source Authority |
| Sites, Areas & People | Mine Site, Spatial Area, Organisation, Person |
| Evidence & Governance | Evidence, Document, Approval |
Key Codes in the Demo Data
The demo runs one site — Red Ridge Mine (RRM), open-cut, Queensland, in the
PROGRESSIVE_REHABILITATION phase — carrying three closure domains at three
different stages of the closure lifecycle so the whole chain is visible at once
rather than one snapshot.
| Code | What it is |
|---|---|
RRM |
The site. Spatial areas SITE → WRD-NORTH → WRD-N-ST2, plus PIT-EAST, INFRA-SOUTH, TOPSOIL-01, REF-WOOD |
D01 |
North Waste Rock Dump — the active arc. 120 ha disturbed / 32 available / 18 rehabilitated / 12 certified |
D01-S2 |
North Dump Stage 2 Eastern Batter (child of D01) — the fully worked chain. 12 ha, CERTIFIED |
D02 |
East Pit — NOT_AVAILABLE until 2034. Nominated non-use management area; the site's EXTREME risk |
D03 |
Southern Infrastructure — 5 ha released, demolition planned FY2027, nothing assessed yet |
RRM-PRCP-001 Rev A / Rev B |
Closure plan Rev A (SUPERSEDED) and Rev B (ACTIVE, supersedes_plan_id → Rev A) |
STAB-00 → STAB-01 |
The superseded visual landform criterion, replaced by the measurable comparison against REF-WOOD |
SAFE-01 · VEG-01 · WATER-01 · ACCESS-01 |
The other completion criteria — public safety, vegetation trajectory, water quality, non-use access control |
RRM-PRS-D01 Rev A / Rev B |
Prescription Rev A (20°, 0.3 m cover — SUPERSEDED) and Rev B (18°, 0.8 m, 30 m drains — ACTIVE) |
RRM-CAM-2025 / -2026 / -2027 |
FY2025 Stage 2 campaign (COMPLETED, $2.81 M), FY2026 Stage 3 (ACTIVE), FY2027 D03 (DRAFT) |
PRMC-DST-2019-00041 |
The disturbance that created the Stage 2 liability — 12 ha, April 2019 |
PRMC-WRK-2024-000112/118/121/126 |
Stage 2 reshape → topsoil → rip → seed. All CERTIFIED, all with accepted hold points |
PRMC-INSP-2024-000352 |
The growth medium depth hold point — PASS_WITH_ACTIONS, two pits below tolerance, topped up |
PRMC-INSP-2026-000418 |
The FAIL — repaired rills re-incised, rework_required = true |
REF-WOOD / MON-VG-REF |
The off-lease reference woodland analogue, and its paired quadrat cluster |
MON-WQ-02 |
The downstream compliance point — the one that cannot resolve the Stage 2 signal |
PRMC-ASM-2026-00046 |
The landform assessment. MET on the five-year record, with the 2026 trend reversal in limitations |
PRMC-ASM-2026-00048 |
The water assessment. PARTIALLY_MET — and it still went into the application |
PRMC-ASM-2022-00008 |
The NOT_MET assessment under the old STAB-00 criterion — why STAB-00 was replaced |
PRMC-CERT-2026-0001 |
The certification. 12 ha APPROVED with three conditions, June 2026 |
PRMC-CERT-2027-0002 |
D03 certification — PREPARING, nothing assessed. Written early so the evidence bar is known |
PRMC-REL-2026-001 |
Relinquishment — READINESS_REVIEW. D02 excluded; the review recommends not lodging |
PRMC-FND-2026-00014 |
The open HIGH finding — post-storm erosion on the certified Stage 2 batter |
PRMC-FND-2026-00016 |
Downstream EC exceedance, 1310 against a 1200 limit — recovered by June |
PRMC-RSK-2022-00011 |
East Pit void access — POSSIBLE × CATASTROPHIC, inherent EXTREME, residual HIGH |
RRM-EST-002 Rev A / Rev B |
Cost estimate Rev A ($68.8 M, SUPERSEDED) and Rev B ($90.8 M, CURRENT) |
PRMC-COM-2026-00005 |
The monitoring commitment created by certification condition 1 — the loop closing |
PRMC-COM-2026-00006 |
The OVERDUE commitment — haul road handover standard, due 31 May 2026 |
PRMC-REV-2025-0003 |
The plan review that killed STAB-00 and the 20° design. Both recommendations were implemented |
The Stage 2 Chain, Step by Step
- April 2019 —
PRMC-DST-2019-00041disturbs 12 ha for the Stage 2 dump lift. - June 2023 — land-availability event:
NOT_AVAILABLE→AVAILABLE. - June 2025 — the three-yearly
ClosureReviewfinds the Revision A design measuring 14.2 t/ha/yr against a reference of 3.9, and that the STAB-00 visual criterion cannot support a certification decision. Both are replaced. - Sep 2024 – Feb 2025 — four work packages against prescription Rev B:
reshape → growth medium → deep rip → direct seed, each closed by a hold-point
inspection. Land availability walks
REHABILITATION_STARTED→REHABILITATED. - 2021 – 2026 — five annual landform surveys (21.5 → 9.6 → 6.1 → 4.4 → 7.8 t/ha/yr) and five vegetation surveys (54% → 68% of reference cover).
- 25 Feb 2026 — 143 mm in 24 hours. Post-event monitoring records 11
rills per 100 m and 0.28 m incision; finding
PRMC-FND-2026-00014raised. - March 2026 — downstream EC hits 1310 µS/cm against a 1200 limit;
PRMC-FND-2026-00016raised and notified within 14 days. - Apr – May 2026 — four criterion assessments: SAFE, STAB and VEG MET,
WATER PARTIALLY_MET with the reason stated in
limitations. - 18 Mar 2026 — certification lodged with both problems fully disclosed.
- 26 Jun 2026 — APPROVED, 12 ha certified, with three conditions. The
monitoring condition becomes commitment
PRMC-COM-2026-00005. - Still open — the erosion repair
PRMC-ACT-2026-00028isIN_PROGRESS, on certified ground, and the relinquishment readiness review says so.
Status Vocabularies (the important ones)
Record lifecycle (most models): DRAFT → REVIEW → APPROVED → ACTIVE, then
SUSPENDED · COMPLETED · CLOSED · CANCELLED · SUPERSEDED · ARCHIVED
Plan status: DRAFT · INTERNAL_REVIEW · STAKEHOLDER_REVIEW · SUBMITTED ·
INFORMATION_REQUEST · APPROVED · ACTIVE · AMENDMENT_REQUIRED · SUPERSEDED · CLOSED
Land availability (the area-state ladder): NOT_AVAILABLE ·
AVAILABLE_PENDING_WORK · AVAILABLE · REHABILITATION_STARTED · REHABILITATED ·
MONITORING · CERTIFICATION_PENDING · CERTIFIED · EXEMPT
Criterion status: PROPOSED · UNDER_REVIEW · APPROVED · ACTIVE ·
NOT_ASSESSED · PARTIALLY_MET · MET · NOT_MET · AT_RISK · SUPERSEDED
Rehabilitation stage: PLANNED · SCHEDULED · MOBILISED · IN_PROGRESS ·
PAUSED · PRACTICALLY_COMPLETE · UNDER_MONITORING · REWORK_REQUIRED · COMPLETE ·
VERIFIED · CERTIFIED
Monitoring result status: DRAFT · VALIDATED · ACCEPTED · SUSPECT ·
REJECTED · EXCEEDANCE · ACTION_REQUIRED · CLOSED
Certification status: PREPARING · SUBMITTED · INFORMATION_REQUEST ·
ASSESSED · APPROVED · PARTIALLY_APPROVED · REFUSED · WITHDRAWN · EXPIRED
Relinquishment status: NOT_READY · READINESS_REVIEW ·
EVIDENCE_COMPILATION · APPLICATION_PREPARATION · SUBMITTED ·
INFORMATION_REQUEST · INSPECTION · ASSESSMENT · CONDITIONS_OUTSTANDING ·
ACCEPTED · PARTIALLY_ACCEPTED · REFUSED · WITHDRAWN
Commitment status: PROPOSED · AGREED · ACTIVE · DUE · OVERDUE · DELIVERED ·
VERIFIED · CLOSED · SUPERSEDED · DISPUTED
Action status: OPEN · ASSIGNED · IN_PROGRESS · BLOCKED ·
AWAITING_VERIFICATION · VERIFIED · CLOSED · CANCELLED · OVERDUE
Risk: LOW · MODERATE · HIGH · EXTREME;
Finding severity: INFORMATION · LOW · MODERATE · HIGH · CRITICAL;
Cost class: CONCEPTUAL · ORDER_OF_MAGNITUDE · BUDGET · DEFINITIVE · ACTUAL
Rules of Thumb
- Disturbed, available, rehabilitated and certified are four different
numbers. They live in four columns on
ClosureDomainand answer four different questions. TheLandAvailabilityEventhistory is the audit trail between them — read it before trusting the totals. - A criterion is not met without an approved
CriterionAssessment. The assessment carries the period, the evidence, the confidence, the limitations and three separate people.METwith no assessment behind it is a data error. PARTIALLY_METis a usable answer. Disclosing it and taking a conditional decision beats deferring the application — the demo takes that path deliberately.- Corrections to approved records are superseding rows with a reason, not edits. Plan, prescription, criterion, cost estimate and source document all demonstrate this, and the review that triggered each supersession is on file.
- Assessed, reviewed and approved are different people — as are prepared / reviewed / approved on prescriptions and estimates, and assigned / verified on corrective actions. The columns are separate on purpose.
- Certification is per domain; relinquishment is whole of site. You can certify 12 ha of a 120 ha dump. You cannot relinquish until every domain has an answer — including the one that says "not before 2034".
- A certified area can still carry an open finding. Certification is a decision at a point in time under stated conditions, not a permanent clearance.