Quick Reference

Menu map, demo-data codes and statuses


Group Models
Rehabilitation Delivery Rehabilitation Work, Work Inspection, Work Material, Rehabilitation Campaign, Rehabilitation Prescription, Disturbance Event
Domains & Land Use Closure Domain, Land Availability Event, Domain Land Use, Domain Objective, Post Mining Land Use
Completion Criteria Completion Criterion, Domain Criterion, Criterion Assessment
Monitoring & Results Monitoring Event, Monitoring Result, Monitoring Schedule, Monitoring Program, Monitoring Location
Certification & Relinquishment Certification Application, Certification Criterion, Relinquishment Application, Relinquishment Domain, Closure Review
Risk, Findings & Actions Closure Risk, Finding, Corrective Action
Stakeholders & Commitments Closure Commitment, Stakeholder, Engagement Event
Closure Cost Closure Cost Estimate, Closure Cost Item, Actual Closure Cost
Plans & Obligations Closure Plan, Closure Objective, Closure Assumption, Plan Requirement Link, Requirement, Source Document, Source Authority
Sites, Areas & People Mine Site, Spatial Area, Organisation, Person
Evidence & Governance Evidence, Document, Approval

Key Codes in the Demo Data

The demo runs one site — Red Ridge Mine (RRM), open-cut, Queensland, in the PROGRESSIVE_REHABILITATION phase — carrying three closure domains at three different stages of the closure lifecycle so the whole chain is visible at once rather than one snapshot.

Code What it is
RRM The site. Spatial areas SITEWRD-NORTHWRD-N-ST2, plus PIT-EAST, INFRA-SOUTH, TOPSOIL-01, REF-WOOD
D01 North Waste Rock Dump — the active arc. 120 ha disturbed / 32 available / 18 rehabilitated / 12 certified
D01-S2 North Dump Stage 2 Eastern Batter (child of D01) — the fully worked chain. 12 ha, CERTIFIED
D02 East PitNOT_AVAILABLE until 2034. Nominated non-use management area; the site's EXTREME risk
D03 Southern Infrastructure — 5 ha released, demolition planned FY2027, nothing assessed yet
RRM-PRCP-001 Rev A / Rev B Closure plan Rev A (SUPERSEDED) and Rev B (ACTIVE, supersedes_plan_id → Rev A)
STAB-00STAB-01 The superseded visual landform criterion, replaced by the measurable comparison against REF-WOOD
SAFE-01 · VEG-01 · WATER-01 · ACCESS-01 The other completion criteria — public safety, vegetation trajectory, water quality, non-use access control
RRM-PRS-D01 Rev A / Rev B Prescription Rev A (20°, 0.3 m cover — SUPERSEDED) and Rev B (18°, 0.8 m, 30 m drains — ACTIVE)
RRM-CAM-2025 / -2026 / -2027 FY2025 Stage 2 campaign (COMPLETED, $2.81 M), FY2026 Stage 3 (ACTIVE), FY2027 D03 (DRAFT)
PRMC-DST-2019-00041 The disturbance that created the Stage 2 liability — 12 ha, April 2019
PRMC-WRK-2024-000112/118/121/126 Stage 2 reshape → topsoil → rip → seed. All CERTIFIED, all with accepted hold points
PRMC-INSP-2024-000352 The growth medium depth hold point — PASS_WITH_ACTIONS, two pits below tolerance, topped up
PRMC-INSP-2026-000418 The FAIL — repaired rills re-incised, rework_required = true
REF-WOOD / MON-VG-REF The off-lease reference woodland analogue, and its paired quadrat cluster
MON-WQ-02 The downstream compliance point — the one that cannot resolve the Stage 2 signal
PRMC-ASM-2026-00046 The landform assessment. MET on the five-year record, with the 2026 trend reversal in limitations
PRMC-ASM-2026-00048 The water assessment. PARTIALLY_MET — and it still went into the application
PRMC-ASM-2022-00008 The NOT_MET assessment under the old STAB-00 criterion — why STAB-00 was replaced
PRMC-CERT-2026-0001 The certification. 12 ha APPROVED with three conditions, June 2026
PRMC-CERT-2027-0002 D03 certification — PREPARING, nothing assessed. Written early so the evidence bar is known
PRMC-REL-2026-001 Relinquishment — READINESS_REVIEW. D02 excluded; the review recommends not lodging
PRMC-FND-2026-00014 The open HIGH finding — post-storm erosion on the certified Stage 2 batter
PRMC-FND-2026-00016 Downstream EC exceedance, 1310 against a 1200 limit — recovered by June
PRMC-RSK-2022-00011 East Pit void access — POSSIBLE × CATASTROPHIC, inherent EXTREME, residual HIGH
RRM-EST-002 Rev A / Rev B Cost estimate Rev A ($68.8 M, SUPERSEDED) and Rev B ($90.8 M, CURRENT)
PRMC-COM-2026-00005 The monitoring commitment created by certification condition 1 — the loop closing
PRMC-COM-2026-00006 The OVERDUE commitment — haul road handover standard, due 31 May 2026
PRMC-REV-2025-0003 The plan review that killed STAB-00 and the 20° design. Both recommendations were implemented

The Stage 2 Chain, Step by Step

  1. April 2019PRMC-DST-2019-00041 disturbs 12 ha for the Stage 2 dump lift.
  2. June 2023 — land-availability event: NOT_AVAILABLEAVAILABLE.
  3. June 2025 — the three-yearly ClosureReview finds the Revision A design measuring 14.2 t/ha/yr against a reference of 3.9, and that the STAB-00 visual criterion cannot support a certification decision. Both are replaced.
  4. Sep 2024 – Feb 2025 — four work packages against prescription Rev B: reshape → growth medium → deep rip → direct seed, each closed by a hold-point inspection. Land availability walks REHABILITATION_STARTEDREHABILITATED.
  5. 2021 – 2026 — five annual landform surveys (21.5 → 9.6 → 6.1 → 4.4 → 7.8 t/ha/yr) and five vegetation surveys (54% → 68% of reference cover).
  6. 25 Feb 2026143 mm in 24 hours. Post-event monitoring records 11 rills per 100 m and 0.28 m incision; finding PRMC-FND-2026-00014 raised.
  7. March 2026 — downstream EC hits 1310 µS/cm against a 1200 limit; PRMC-FND-2026-00016 raised and notified within 14 days.
  8. Apr – May 2026 — four criterion assessments: SAFE, STAB and VEG MET, WATER PARTIALLY_MET with the reason stated in limitations.
  9. 18 Mar 2026 — certification lodged with both problems fully disclosed.
  10. 26 Jun 2026APPROVED, 12 ha certified, with three conditions. The monitoring condition becomes commitment PRMC-COM-2026-00005.
  11. Still open — the erosion repair PRMC-ACT-2026-00028 is IN_PROGRESS, on certified ground, and the relinquishment readiness review says so.

Status Vocabularies (the important ones)

Record lifecycle (most models): DRAFT → REVIEW → APPROVED → ACTIVE, then SUSPENDED · COMPLETED · CLOSED · CANCELLED · SUPERSEDED · ARCHIVED

Plan status: DRAFT · INTERNAL_REVIEW · STAKEHOLDER_REVIEW · SUBMITTED · INFORMATION_REQUEST · APPROVED · ACTIVE · AMENDMENT_REQUIRED · SUPERSEDED · CLOSED

Land availability (the area-state ladder): NOT_AVAILABLE · AVAILABLE_PENDING_WORK · AVAILABLE · REHABILITATION_STARTED · REHABILITATED · MONITORING · CERTIFICATION_PENDING · CERTIFIED · EXEMPT

Criterion status: PROPOSED · UNDER_REVIEW · APPROVED · ACTIVE · NOT_ASSESSED · PARTIALLY_MET · MET · NOT_MET · AT_RISK · SUPERSEDED

Rehabilitation stage: PLANNED · SCHEDULED · MOBILISED · IN_PROGRESS · PAUSED · PRACTICALLY_COMPLETE · UNDER_MONITORING · REWORK_REQUIRED · COMPLETE · VERIFIED · CERTIFIED

Monitoring result status: DRAFT · VALIDATED · ACCEPTED · SUSPECT · REJECTED · EXCEEDANCE · ACTION_REQUIRED · CLOSED

Certification status: PREPARING · SUBMITTED · INFORMATION_REQUEST · ASSESSED · APPROVED · PARTIALLY_APPROVED · REFUSED · WITHDRAWN · EXPIRED

Relinquishment status: NOT_READY · READINESS_REVIEW · EVIDENCE_COMPILATION · APPLICATION_PREPARATION · SUBMITTED · INFORMATION_REQUEST · INSPECTION · ASSESSMENT · CONDITIONS_OUTSTANDING · ACCEPTED · PARTIALLY_ACCEPTED · REFUSED · WITHDRAWN

Commitment status: PROPOSED · AGREED · ACTIVE · DUE · OVERDUE · DELIVERED · VERIFIED · CLOSED · SUPERSEDED · DISPUTED

Action status: OPEN · ASSIGNED · IN_PROGRESS · BLOCKED · AWAITING_VERIFICATION · VERIFIED · CLOSED · CANCELLED · OVERDUE

Risk: LOW · MODERATE · HIGH · EXTREME; Finding severity: INFORMATION · LOW · MODERATE · HIGH · CRITICAL; Cost class: CONCEPTUAL · ORDER_OF_MAGNITUDE · BUDGET · DEFINITIVE · ACTUAL

Rules of Thumb

  • Disturbed, available, rehabilitated and certified are four different numbers. They live in four columns on ClosureDomain and answer four different questions. The LandAvailabilityEvent history is the audit trail between them — read it before trusting the totals.
  • A criterion is not met without an approved CriterionAssessment. The assessment carries the period, the evidence, the confidence, the limitations and three separate people. MET with no assessment behind it is a data error.
  • PARTIALLY_MET is a usable answer. Disclosing it and taking a conditional decision beats deferring the application — the demo takes that path deliberately.
  • Corrections to approved records are superseding rows with a reason, not edits. Plan, prescription, criterion, cost estimate and source document all demonstrate this, and the review that triggered each supersession is on file.
  • Assessed, reviewed and approved are different people — as are prepared / reviewed / approved on prescriptions and estimates, and assigned / verified on corrective actions. The columns are separate on purpose.
  • Certification is per domain; relinquishment is whole of site. You can certify 12 ha of a 120 ha dump. You cannot relinquish until every domain has an answer — including the one that says "not before 2034".
  • A certified area can still carry an open finding. Certification is a decision at a point in time under stated conditions, not a permanent clearance.